2Africa Consortium adds four new cable branches
The 2Africa consortium, comprised of China Mobile International, Facebook, MTN GlobalConnect, Orange, STC, Telecom Egypt, Vodafone, and WIOCC, has announced the addition of four new branches to the 2Africa cable.
The branches will extend 2Africa’s connectivity to Seychelles, the Comoros Islands, and Angola, and bring a new landing to south-east Nigeria.
The new branches join the recently announced extension to the Canary Islands.
2Africa consortium, which will be the largest subsea cable project in the world was launched in May last year and will deliver faster, more reliable internet service to each country where it lands.
Communities that rely on the internet for services from education to healthcare, and businesses will experience the economic and social benefits that come from this increased connectivity.
Alcatel Submarine Networks (ASN) has been selected to deploy the new branches, which will increase the number of 2Africa landings to 35 in 26 countries, further improving connectivity into and around Africa.
As with other 2Africa cable landings, capacity will be available to service providers at carrier-neutral data centres or open-access cable landing stations on a fair and equitable basis, encouraging and supporting the development of a healthy internet ecosystem.
Marine surveys completed for most of the cable and Cable manufacturing is underway
Since launching the 2Africa cable in May 2020, the 2Africa consortium has made considerable progress in planning and preparing for the deployment of the cable, which is expected to ‘go live’ late 2023.
Most of the subsea route survey activity is now complete. ASN has started manufacturing the cable and building repeater units in its factories in Calais and Greenwich to deploy the first segments in 2022.
Egypt terrestrial crossing already completed
One of 2Africa’s key segments, the Egypt terrestrial crossing that interconnects landing sites on the Red and the Mediterranean Seas via two completely diverse terrestrial routes, has been completed ahead of schedule.
A third diverse marine path will complement this segment via the Red Sea.